1. Industry pain points
The server room is a precision capacitive load, and data loss occurs when power is cut off; Dense cables in the computer room are prone to short circuits and fires; The fire pump is idle and corroded all year round, and cannot be started in case of a fire.
2. Customized Product Configuration for Ximu
- Uninterrupted Power Supply: XMAC Power Frequency/High Frequency Three In Three Out UPS (10kVA~800kVA, Dual Redundancy Architecture, 0ms Switching)+High Power DC Screen
- Fire Protection System: FEPS Three Phase Power EPS+XM-XFXJ Fire Inspection Cabinet (Inspection Cabinet+Spray/Fire Hydrant Control Cabinet+ATS Dual Power Supply)
- End Protection: XM-AC-S Three Phase Fire Limiting Current Protector (Machine Room Distribution Cabinet Anti Short Circuit and Arc Extinguishing)
3. Scheme Value
Triple backup of mains power, UPS, and EPS, ensuring continuous operation of computing power for 7 × 24 hours; Automatic periodic inspection of fire-fighting equipment to prevent rusting of the pump body; End microsecond level current limiting arc extinguishing to reduce electrical fire hazards in the computer room.
4. Landing cases
Alibaba Yangtze River Delta Intelligent Computing Base, Tiktok Volcano Engine Inner Mongolia Computing Center, Mianyang Jiuyuan IDC, Fuzhou Changleyuan Network Storage IDC and other projects.